Maintenance Schedule subject to change without notice due to outside conditions.
Pct Rd Work Projects Road Schedule McPUPs Events
August 2010
Rain delayed starting some of our projects
|
Aug 30–Sept 3, 2010 |
Litter Pick Up – Lorena & Bruceville-Eddy areas |
|
|
Patching – Precinct-wide |
|
|
Tree Trimming – Lorena & Bruceville-Eddy areas |
|
|
Blading – Bruceville-Eddy area |
|
|
Shredding – Robinson & Downsville areas |
|
|
Ditch Work will continue – George Roberts |
|
|
Construction is complete – |
|
|
Reconstruction will begin - City Limits of Moody |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Aug 23–Aug 27, 2010 |
Litter Pick Up – Lorena & Bruceville-Eddy areas |
|
|
Patching – Precinct-wide |
|
|
Shredding – Robinson area |
|
|
Ditch Work – George Roberts |
|
|
Reconstruction will continue – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Aug 16–Aug 20, 2010 |
Litter Pick Up – Lorena area |
|
|
Patching – Precinct-wide |
|
|
Shredding – Robinson & Lorena areas |
|
|
Ditch Work – George Roberts |
|
|
Reconstruction will continue – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
August 9–August 13, 2010 |
Litter Pick Up – Downsville & Robinson
areas |
|
|
Patching – Precinct-wide |
|
|
Shredding – Moody & Lorena areas |
|
|
Ditch Work – George Roberts |
|
|
Road work will continue – |
|
|
Reconstruction has begun – Winchester Dr. |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
August 2 – August 6, 2010 |
Litter Pick Up – Downsville & Robinson
areas |
|
|
Patching – Precinct-wide |
|
|
Shredding – Moody & Lorena areas |
|
|
Ditch Work – George Roberts |
|
|
Road work will continue – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
July 2010
Rain delayed starting some of our projects
|
July 26 – July 30, 2010 |
Litter Pick Up – Moody area |
|
|
Patching – Precinct-wide |
|
|
Shredding – Moody & Lorena areas |
|
|
Road work will continue – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
July 19 – July 23, 2010 |
Litter Pick Up – Lorena & Bruceville-Eddy areas |
|
|
Patching – Precinct-wide |
|
|
Shredding – Bruceville-Eddy, Robinson &
Downsville areas |
|
|
Road work has been completed – |
|
|
Road work will continue – |
|
|
Road work will begin – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
July 12 – July 16, 2010 |
Patching – Precinct-wide |
|
|
Ditches Work – |
|
|
Shredding – Bruceville-Eddy,
Robinson & Downsville areas |
|
|
Road work has begun – |
|
|
Road work will begin on July 12th on |
|
|
Road work has been completed – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
July 5 – July 9, 2010 |
Litter Pick Up – Downsville, Robinson & Asa areas |
|
|
Patching – Precinct-wide |
|
|
Ditches Work – |
|
|
Shredding – Bruceville-Eddy,
Robinson & Downsville areas |
|
|
Road work has begun – |
|
|
Road work will continue – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
June 2010
Rain delayed starting some of our projects
|
June 28 – July 1, 2010 |
Litter Pick Up – Bruceville-Eddy area |
|
|
Patching – Precinct-wide |
|
|
Ditches Work – |
|
|
Shredding – Bruceville-Eddy area |
|
|
Road work has begun – |
|
|
Road work will continue – |
|
|
Road work has been completed – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
June 21 – June 25, 2010 |
Litter Pick Up – Lorena area |
|
|
Patching – Precinct-wide |
|
|
Ditches Work – |
|
|
Shredding – Moody area |
|
|
Road work will continue when repaired – |
|
|
Road work has been completed – Box Ranch |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
June 14 – June 18, 2010 |
Litter Pick Up – Robinson & Downsville
areas |
|
|
Patching – Precinct-wide |
|
|
Ditches Work – |
|
|
Shredding – Moody area |
|
|
Road work was held up by a water leak and will
continue when repaired – |
|
|
Road work will continue – Box Ranch & Cooksey
Lane |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
June 7 – June 11,2010
|
Litter Pick Up – Moody area |
|
|
Patching – Precinct-wide |
|
|
Ditches Work – George Roberts, Liberty Hill & |
|
|
Shredding – Moody area |
|
|
Road work was held up by a water leak and will
continue when repaired – |
|
|
Road work will begin – Box Ranch &
Cooksey Lane |
|
|
Pct 1 is having a COUNTY
CLEAN UP DAY, Saturday, June 5, 2010, 8:00 am to 2:00 pm. Residents in Pct 1
are welcome to bring any household trash, limbs, used oil, old paint and
scrape metal to be disposed of. Clean
up collection will be at the Road & Bridge Yard @ 1239 |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
June 1 – June 4,2010 |
Litter Pick Up – Bruceville-Eddy
area |
|
|
Patching – Precinct-wide |
|
|
Ditches Work – George Roberts |
|
|
Shredding – Precince-wide |
|
|
Road work was held up by a water leak and will
continue when repaired – |
|
|
Road work will continue – |
|
|
Road work will begin – Box Ranch &
Cooksey Lane |
|
|
Pct 1 is having a COUNTY
CLEAN UP DAY, Saturday, June 5, 2010, 8:00 am to 2:00 pm. Residents in Pct 1
are welcome to bring any household trash, limbs, used oil, old paint and scrape
metal to be disposed of. Clean up
collection will be at the Road & Bridge Yard @ 1239 |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
May 2010
Rain delayed starting some of our projects
|
May 24 – May 28,2010 |
Litter Pick Up – Robinson & Downsville
areas |
|
|
Patching – Bruceville-Eddy, Lorena & Moody
areas |
|
|
Ditches Work – George Roberts & |
|
|
Shredding – Moody & Bruceville-Eddy
areas |
|
|
Road work will continue – |
|
|
Road work will begin – |
|
|
There will be road closures at these locations. We apologize
for any inconvenience |
|
May 17 – May 21,2010 |
Litter Pick Up – Lorena & Moody areas |
|
|
Patching – Bruceville-Eddy, Lorena & Moody
areas |
|
|
Ditches Work – George Roberts & |
|
|
Shredding – Moody & Bruceville-Eddy
areas |
|
|
Road work will continue – |
|
|
Road work will begin – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
May 10 – May 14,2010 |
Litter Pick Up – Robinson area |
|
|
Patching – Bruceville-Eddy, Lorena & Moody
areas |
|
|
Ditches Work – George Roberts & |
|
|
Shredding – Lorena & Robinson areas |
|
|
Road work will continue – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
May 3 – May 7, 2010 |
Litter Pick Up – Lorena & Robinson areas |
|
|
Patching – Bruceville-Eddy,
Lorena & Moody areas |
|
|
Ditches Work – LW Hatter Trail, |
|
|
Shredding – Lorena & Robinson areas |
|
|
Road work will continue – Dowell Road &
Wall Ridge |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
April 2010
Rain delayed starting some of our projects
|
Apr. 26 – Apr 30, 2010 |
Litter Pick Up – Robinson & Lorena areas |
|
|
Patching – Bruceville-Eddy,
Lorena & Moody areas |
|
|
Ditches Work – LW Hatter Trail, |
|
|
Shredding – Moody & Bruceville-Eddy
areas |
|
|
Road work will continue – |
|
|
Road work will continue – Wall Ridge |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Apr. 19 – Apr 23, 2010 |
Litter Pick Up – Moody area |
|
|
Patching – Bruceville-Eddy
& Lorena areas |
|
|
Dip Ditches – LW Hatter Trail |
|
|
Shredding – Moody & Bruceville-Eddy
areas |
|
|
Road work will begin – |
|
|
Road work will continue – Wall Ridge |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Apr. 12 – Apr 16, 2010 |
Litter Pick Up – Precinct-wide |
|
|
Patching – Bruceville-Eddy
area |
|
|
Dip Ditches – LW Hatter Trail |
|
|
Blading Roads – Lorena & Bruceville-Eddy
areas |
|
|
Shredding – Lorena, Moody & Bruceville-Eddy
areas |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Apr. 5 – Apr 9, 2010 |
Litter Pick Up – Bruceville-Eddy
& Moody areas |
|
|
Patching – Robinson area |
|
|
Dip Ditches – |
|
|
Blading Roads – Moody area |
|
|
Shredding – Robinson area |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
March 2010
Rain delayed starting some of our projects
|
Mar.29 – Apr 1, 2010 |
Litter Pick Up – Robinson & Lorena areas |
|
|
Patching – Robinson & Lorena areas |
|
|
Dipping Ditches – Franklin, |
|
|
Blading Roads
– Lorena
& Moody areas |
|
|
Shredding – Has begun in the Lorena & Robinson areas |
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Mar.22 – Mar.26, 2010 |
Litter Pick Up – Lorena area |
|
|
Patching –
Lorena area |
|
|
Dipping Ditches – LW Hatter Trail, |
|
|
Blading Roads
–
Lorena & Moody areas |
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Mar.15 – Mar.19, 2010 |
Litter Pick Up – Bruceville-Eddy
and Moody areas |
|
|
Patching – Bruceville-Eddy and Moody areas |
|
|
Dipping Ditches and Install Culverts – |
|
|
Dipping Ditches – LW Hatter Trail |
|
|
Blading Roads
–
Precinct-wide |
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Mar.8 – Mar. 12, 2010 |
Litter Pick Up – Bruceville-Eddy and Moody areas |
|
|
Patching – Bruceville-Eddy and Moody areas |
|
|
Dipping Ditches and Install Culverts – LW Hatter Trail, |
|
|
Blading Roads
– Precinct-wide
|
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Mar.1 – Mar. 5, 2010 |
Litter Pick Up – Lorena area |
|
|
Patching – Precinct-wide, weather permitting |
|
|
Dipping Ditches and Install Culverts – Porter and S. Blue Cut – weather permitting |
|
|
Blading Roads
– Precinct-wide
|
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We apologize
for any inconvenience |
February 2010
Rain delayed starting some of our projects.
|
Feb.22 – Feb. 26, 2010 |
Litter Pick Up – Bruceville-Eddy area |
|
|
Patching – Lorena and Downsville areas |
|
|
Reconstruct – Howe Hill |
|
|
Dipping Ditches and Install Culverts – Porter and the intersection of Franklin and Wade |
|
|
Blading Roads
– Moody
area |
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We
apologize for any inconvenience |
|
Feb.15 – Feb. 19, 2010 |
Litter Pick Up – Loren and Moody areas |
|
|
Patching – Lorena and Bruceville-Eddy areas |
|
|
Reconstruct – |
|
|
Clearing right of way and reshaping ditches - |
|
|
Dipping Ditches and Install Culverts – Tower, Doss, Porter and the intersection of
Franklin and Wade |
|
|
Blading Roads
– Precinct
wide |
|
|
Bridge Construction – |
|
|
There will be road closures at these locations. We apologize for any inconvenience |
|
Feb. 8 – Feb. 12, 2010 |
Litter Pick Up – Downsville and Robinson areas |
|
|
Patching - Downsville and Robinson area |
|
|
Reconstruct – |
|
|
Clearing right of
way and reshaping ditches - |
|
|
Dipping Ditches and
Install Culverts - Elm Creek, Porter and the
intersection of Franklin and Wade |
|
|
Blading Roads – Precinct wide |
|
|
Bridge Construction – |
|
|
There will be road
closures at these locations. We
apologize for any inconvenience |
|
Feb. 1 – Feb. 5, 2010 |
Litter Pick Up – |
|
|
Patching – Bruceville-Eddy area |
|
|
Reconstruct – |
|
|
Clearing right of way
and reshaping ditches – |
|
|
Dipping Ditches and Install Culverts – Linda Vista Rd., Tower Rd., Doss Rd., and Wall Ridge Road |
|
|
Blading Roads – Precinct wide |
|
|
There will be road closures
at these locations. We apologize for
any inconvenience. |
January 2010
Rain delayed starting some of our projects.
|
Jan. 4 – Jan. 8, 2010 |
Install Guard Rail – Foggy |
|
|
Asphalt Work
– will continue on |
|
|
Litter Pick Up – Precinct wide |
|
|
Tree Trimming – Moody and Bruceville-Eddy areas |
|
|
Patching – Various areas precinct wide |
|
|
Reconstruct – will continue on |
|
|
Clearing the right of way and reshaping
ditches –
McGregor S. Loop |
|
|
There will be road closures at
these locations. We apologize for any
inconvenience. |
|
Jan. 11 – Jan. 15,
2010 |
Litter Pick Up – Bruceville-Eddy and Moody areas |
|
|
Tree Trimming – |
|
|
Patching – Bruceville-Eddy area |
|
|
Reconstruct – will continue on |
|
|
Clearing right of way and reshaping
ditches –
McGregor S. Loop and LW Hatter |
|
|
There will be road closures
at these locations. We apologize for
any inconvenience. |
|
Jan. 18 – Jan. 22,
2010 |
Litter Pick Up – |
|
|
Patching – |
|
|
Reconstruct – |
|
|
Clearing right of way and reshaping
ditches – |
|
|
Dipping Ditches – Box Ranch |
|
|
Blading Roads – Precinct wide |
|
|
There will be road closures
at these locations. We apologize for
any inconvenience. |